Renovation timelines, explained room by room
A realistic guide to how long kitchens, bathrooms and whole-home renovations take, and where projects usually slip.

A realistic guide to how long kitchens, bathrooms and whole-home renovations take, and where projects usually slip.
Design takes longer than you think
Allow six to ten weeks for design and approvals before anyone lifts a hammer. Decisions made early save weeks on site.
Lead times drive the schedule
Custom millwork, stone and imported lighting can take twelve weeks or more. We order long-lead items as soon as the design is signed off.
Build in a buffer
Old houses hide surprises. A 10 percent time and budget contingency keeps a small discovery from becoming a crisis.